PHASE IV - Undergrounding of Overhead Utilities Project

 

Construction Map Here

 

Construction site with a trench, pipes, workers in safety gear, vehicles, and traffic cones under a clear blue sky.

OVERVIEW

Phase IV of the UOU includes installation of underground joint utility trenches to replace existing main line overhead power (PG&E), telephone (AT&T), and cable (Comcast) lines along stretches of Lopez Road, Sunridge Road, Ronda Road, Spruance Road, Midwood Lane, and Del Ciervo Road.

PROJECT STATUS

Construction will occur from September 2026 through the summer of 2028.

Working hours are Monday - Friday from 8:00am - 5:00pm.

 

IMPROVEMENT LOCATIONS

 The project will be divided into several routes, each with its own construction dates.

20260817 UOU PHASE IV Resident Map Draft FINAL.pdf

 

LOCATION START DATE ESTIMATED FINISH
Lopez Road September 8, 2026 TBD
Sunridge Road TBD TBD
Ronda Road TBD TBD
Spruance Road TBD TBD
Midwood Lane TBD TBD
Del Ciervo Road TBD TBD
Atajo Way TBD TBD

 

QUESTIONS?

Contact Project Manager Chris Simmons, P.E.

(831) 647-5609 | csimmons@pbcsd.org 

 