D I S T R I C T E N G I N E E
R ' S R E P O R T
TO: PBCSD Board of Directors
FROM: Michael Niccum, District Engineer
SUBJECT: Utilities Operations
and Maintenance
Report
for 7/20/05 to 8/17/05
_________________________________________________________________________
1.
SUMMARY
OF MAINTENANCE ACTIVITY:
The
maintenance department painted the generator housing at pump station P-5
(Easement below Sunset Lane), rebuilt a pump at P-8 (Inn at Spanish Bay), performed
semiannual maintenance of valves on the recycled water pipelines, removed
vegetative growth at Indian Village, received an 8-hour training course from
ACWA/JPIA (Association of California Water Agencies – Joint Powers Insurance
Authority) on traffic control and trenching safety, arranged for installation
of a pressure reducing water valve for the fire department quarters, skylight
replacement in the office of the engineering and maintenance assistant and
semiannual maintenance of utility truck PB-1 and dump truck PB-6.
2. WASTEWATER FLOW
MEASUREMENTS:
An
average daily wastewater flow of 584,000 gallons per day (gpd) was measured at
the PBCSD Carmel gate flow metering station in July, which represents 33 % of
the total flow of 1,793,000 gpd measured at the CAWD treatment plant. The PBCSD flow is 3 % above the five-year
average of 565,000 gpd for July and the CAWD total flow is 2 % below the
five-year average of 1,836,000 gpd for July.
A chart showing the quantity of PBCSD wastewater flow recorded during
the month of July and a graph showing average daily wastewater flows from PBCSD
and the CAWD treatment plant for the past twelve months as well as the
five-year average for each month is attached.
3. RECYCLED WATER
USE:
Total
irrigation water demand for the 2004-05 water year (October 1 to September 30)
to date is 699 acre-feet including 523 acre-feet or 75 % of recycled
water. Total demand for the water year
is 11 % below the 10-year average usage of 788 acre-feet for this point in the
water year. The August flushing cycle
used 15 acre-feet of potable water.
Approximately 90 acre-feet of potable water have been used in flushing
cycles during the current water year, which accounts for 51 % of the total
potable water use of 176 acre-feet.
Two
attached charts show the total water and potable water usage recorded on a
daily basis for July and August to date.
Two additional charts and a graph summarize total, recycled and potable
water usage on a monthly basis for the 2004-05 water year to date and for the
previous ten water years.
4. RESIDENT COMPLAINTS
& REQUESTS:
DATE ADDRESS DESCRIPTION
7/26/05 3298 17-Mile Drive A contractor reported sewage overflowing from
lateral.
APN: 008-393-009 Maintenance department cleared a stoppage in
main
line,
observed approximately 30 gallons overflowed to a
confined
area, cleaned and disinfected the area.
8/4/05 3192
17-Mile Drive Cal-Am Water reported water
flowing out of a manhole.
APN: 008-491-009 Maintenance
department determined the source of water
was
the house lateral, which is a force main from a
residential
pump station, and notified caretaker at
residence.
8/9/05 1700 Crespi Lane Resident reported a sewer line was damaged
by tree
APN: 008-371-012 stump removal.
Maintenance department notified the
owner
the break was located in the house lateral.
5. SEWER CONNECTION
PERMITS/INSPECTIONS:
DATE ADDRESS DESCRIPTION
7/21/05 3116 Middle Ranch Road Permit #2833 issued for replacing sewer
lateral.
APN: 007-431-011 Owner: Kathryn Urry
7/22/05 1418 Viscaino Road Permit #2834 issued for new service
connection.
APN: 008-231-010 Owner: Giuseppe Catania
6. SEWER LINES
CLEANING:
Lines
were cleaned by the maintenance department using the combination line
cleaning/vacuum truck at the following locations in the neighborhoods in upper
DATE FOOTAGE DESCRIPTION
7/25/05 5,072 feet
8/1/05 3,723 feet Pine Meadows Way,
8/2/05 1,709 feet Sunset Lane,
8/4/05 2,452 feet
8/8/05 1,776 feet Easements above Sunset Lane
8/10/05 2,089 feet
8/11/05 2,564 feet Easements below Sunset Lane
8/15/05 2,315 feet Lodge,
8/16/05 4,071 feet Easement below
8/17/05 4,544 feet
--------------
TOTAL
FOR THIS PERIOD 31,757 feet
TOTAL
PBCSD LINES 398,000
feet
PERCENTAGE
CLEANED 8 %
7. SOURCE CONTROL:
The
maintenance department inspected grease interceptors at the Lodge and Club XIX
and notified the Lodge building engineer the units required maintenance.
8. UNDERGROUND SERVICE
ALERT CALLS:
During
this period, the maintenance crew marked sewer or reclaimed water lines at the
following locations in response to underground service alert (
DATE LOCATION
7/20/05 13th Avenue and
7/20/05 3210 Whitman Lane
7/20/05 3191 Palmero Way
8/1/05 1064 Majella Road
8/1/05 17-Mile Drive and
8/2/05 1418 Viscaino Road
8/4/05 4024 Ronda Road
8/4/05 17-Mile Drive and
8/5/05 2877 Galleon Road
8/5/05 1700 Crespi Lane
8/8/05 3105 17-Mile Drive
8/9/05
8/9/05 1041 Marcheta Lane
8/9/05 1077 Trappers Trail
8/10/05 2964 Quarry Road
8/16/05 1614 Corte Lane
9. PLAN CHECKS
FOR ADDITIONS/REMODELING:
DATE ADDRESS DESCRIPTION
8/4/05 3114 Bird Rock Road Addition to single family residence
(360 sf)
APN: 007-331-019 Owner: J.R. Shake
8/4/05 3181 Bird Rock Road Addition to single family residence
(72 sf)
APN: 007-381-002 Owners: Pete and Helen Bakker
8/4/05 2862 Oak Knoll Road Addition to single family residence
(317 sf)
APN: 007-201-018 Owners: Edward and Doreen Cutler
8/4/05 3191 Palmero Way Demolish and reconstruct single
family residence
APN: 008-361-008 Owners: Robert and Aurora Teh (4,584
sf)
8/4/05 3298 Stevenson Drive Addition to single family residence
(450 sf)
APN: 008-442-016 Owners: Jack and Lillian Sioukas
8/4/05 1515 Bonifacio Road Demolish and reconstruct senior unit
(850 sf)
APN: 008-222-016 Owner: Alicia Greenan
8/4/05 3326 17-Mile Drive Addition to single
family residence (1,642 sf)
APN: 008-423-024 Owners: Michael Clair and Audrey
MacLean
8/4/05 1021 San Carlos Road Addition to single family residence
(770 sf)
APN: 007-281-014 Owners: Robert and Ruth Stephan
Reviewed:
General
Manager: RA Date:
8/19/05