D I S T R I C T   E N G I N E E R ‘ S   R E P O R T

May 26, 2006

 

            To:      PBCSD Board of Directors

 

            From:  Michael Niccum, District Engineer

 

            Subject:          Fourth Priority Fire Protection Pipeline Replacement Project

_________________________________________________________________________

 

RECOMMENDATION

 

It is recommended the Board of Directors approve the scope of work for the Fire Protection Water System Improvements - Fourth Priority Pipeline Replacement Project.

SUMMARY  OF  ISSUES

 

E2 Consulting Engineers (“E2”) was retained in January to perform preliminary engineering services required to identify the costs and benefits for future fire protection pipeline replacement projects.  E2 has reviewed fire hydrant testing procedures, updated the computer hydraulic model of the water distribution system in Pebble Beach and prepared a technical memorandum identifying pipeline segments with the greatest potential for improvement and preliminary construction cost estimates.  Water main lines with calculated flows less than the minimum fire code hydrant flow requirements were identified and prioritized for replacement based on the ratio of existing fire flow to the fire code flow requirements.

SCOPE  OF  PROJECT

 

A table is attached which identifies the highest priority pipeline segments and the estimated construction cost for upgrading the pipelines. The 4th priority segments are identified on two attached exhibits and are located in areas where fire hydrant testing data matched the flows calculated in the hydraulic model.  Three additional exhibits show the location of the first three pipeline improvement projects already constructed.  The proposed fourth priority pipeline base project will upgrade the main water lines that provide fire flow to all of the country club neighborhoods located in the gravity zone of the water distribution system south of the Monterey Peninsula Country Club and to the Pebble Beach neighborhood located in the first lift zone near the lower interface with the Pescadero Canyon open space.   The optional project elements will increase flows in the neighborhood located in the first lift reduced pressure zone near Forest Lake and the lower interface with the Huckleberry Hill open space as well as the neighborhood located near Bird Rock.  Field hydrant test and hydraulic model data indicate expected fire flows between 500 to 750 gallons per minute (gpm) in the affected area and the proposed improvements will increase the flow rate above the fire code requirement of 1,000 gpm.  

 

Analysis of the computer hydraulic model results and the fire hydrant testing records indicated that in some locations a wide discrepancy exists between expected fire hydrant flows and the actual field measurements.  The reason for the discrepancy could be that the assumed fire hydrant flows are based on old or inaccurate test data or that pipeline friction factors assumed in the hydraulic model do not match field conditions.  The cause of the discrepancy has not yet been confirmed due to a delay in the 2006 fire hydrant testing program.  Field testing cannot begin until the five million gallon water storage tank located near Forest Lake is operational following the recent California American Water (“Cal-Am”) rehabilitation project.  The project elements identified for the 5th priority base project in the summary table may change based on the results of the fire hydrant testing. 

 

E2 has earned $36,920 or 74 % of the budget of $49,760 for preliminary design engineering services.  The remaining work includes providing technical support services to Cal-Am and the Fire Department for the 2006 fire hydrant testing program and revising the computer hydraulic model to reflect the collected field data.

 

The information developed during preliminary engineering indicates the proposed scope of 4th priority pipeline improvements will provide valuable fire protection benefits to several neighborhoods and provide additional fire flow near the interface with large forested open spaces.  It is therefore suggested the scope of project elements identified for the 4th priority fire protection pipeline replacement project be approved.  A recommendation to approve an agreement with E2 Consulting Engineers for engineering services required for design and construction support could be made at the next Board meeting.  It is estimated design and construction work would be completed within twelve months.  An allocation of $1,750,000 for fire protection water system improvements is included in the 2006-07 fiscal year budget. 

 

 

C:  Gary Hofsheier, Monterey District, Cal-Am Water Company

     

Concur:

 

General Manager: RA      Date: 6/19/06                                  

 

Agenda Item No. 13