D I S T R I C
T E N G I N E E R ‘ S R E P O R T
To: PBCSD
Board of Directors
From: Michael
Niccum, District Engineer
Subject: Forest Lake Reservoir Project
_________________________________________________________________________
Anderson Pacific Engineering Construction (Anderson
Pacific) has completed the remaining punch list items for the Forest Lake
Reservoir Components of the Expanded CAWD/PBCSD Wastewater Reclamation Project
with the exception of one item.
Additional modifications were still being completed on the chlorinator
system at the time of the final project walkthrough on July 20th.
Approximately 62 million gallons or 192 acre-feet of
recycled water is currently stored in the reservoir. No water has been observed to date from the
leak detection system below the liner. A
chart showing the
Anderson Pacific has earned 100 % of the revised
construction contract amount of $11,675,863.
All but a retention of $200,000 has been released to the contractor
with the remaining 5 % retention of $607,942 will be released 30 days after
notice of final project completion.
E2 Consulting Engineers completed as-built plans for the
project and prepared additional information required for submittal to the California
Department of Water Resources, Division of Safety of Dams (DSOD). E2 has earned $1,013,449 or 99 % of the
revised budget of $1,027,320 for engineering construction management
services.