D
I S T R I C T E N G I N E E R ‘ S R E P O R T
September 30, 2005
To: PBCSD Board of Directors
From:
Subject: Status
of Capital Improvement Program Projects
_________________________________________________________________________
1. Third Priority Fire Protection Water
Pipeline Replacement Project
A notice of
substantial completion was issued to Monterey Peninsula Engineers, Inc. (MPE) for
the Third Priority Fire Protection Water Pipeline Replacement Project with the
exception of 600 feet of water main line that will be installed in the new
access road to the Monterey Peninsula Country Club (MPCC) clubhouse. This work was added to the contract after the
bid award and fieldwork is scheduled for the last week of September to
accommodate the MPCC access road construction schedule. Remaining punch list work items are scheduled
to be completed within several weeks.
MPE has earned
$1,518,175 or 96 % of the revised contract amount of $1,573,959. E2 Consulting Engineers has earned $258,461 of
the budget of $265,000 for design and construction support engineering
services.
2. 2005 Sewer Line Replacement Project
D’Arcy and
Harty Construction made good progress on the 2005 Sewer Line Replacement Project
completing installation of 1500 feet of sewer lines on an easement below
Chaparral Road between Congress Road and Colton Road, 350 feet on an easement
between Sombrero Road and San Carlos Road and 1,000 feet on Elk Run Road and an
easement between Sloat Road and Coyote Road. The contractor has not made a pay request to
date but has completed approximately 50 % of the $526,250 construction contract. Work on the project will be completed within four
to six weeks. E2 Consulting Engineers
has earned $35,364 of the budget of $89,260 for design and construction support
engineering services.
The remaining
work item for the
4. Pump Station SCADA System Improvement Project
New instrumentation controls are operating at all eight wastewater
pump stations. Alvarez Technology
telephone technicians and instrumentation programmer Doug Buck are completing integration
of the new SCADA system with the SBC data network and the District local area
computer network.
Reviewed:
General Manager: RA Date: 9/23/05 Agenda
Item No. 12B