D
I S T R I C T E N G I N E E R ‘ S R E P O R T
October 28, 2005
To: PBCSD Board of Directors
From:
Subject: Status
of Capital Improvement Program Projects
_________________________________________________________________________
1. Third Priority Fire Protection Water
Pipeline Replacement Project
Monterey
Peninsula Engineers, Inc. (MPE) completed installation of 600 feet of water
main line in the new access road to the Monterey Peninsula Country Club clubhouse. Remaining punch list items for the Third
Priority Fire Protection Water Pipeline Replacement Project will be completed
within several weeks. Retention of
$50,000 will be released to MPE after final completion is achieved. E2 Consulting Engineers has earned $260,042
of the budget of $265,000 for design and construction support engineering
services.
2. 2005 Sewer Line Replacement Project
A
recommendation to increase the construction contract for the 2005 Sewer Line Replacement
Project is included in Agenda Item Number 11C.
The remaining
work item for the
4. Pump Station SCADA System Improvement Project
New instrumentation controls are operating at all eight wastewater
pump stations and the SBC communication system is operating between all
locations. Alvarez Technology
technicians and instrumentation programmer Doug Buck are completing integration
of the new SCADA system with the District local area computer network.
Reviewed:
General Manager: RA
Date: 11/21/05 Agenda
Item No. 11B