D I S T R I C T   E N G I N E E R ‘ S   R E P O R T

December 9, 2005

 

            To:                  PBCSD Board of Directors

                         

            From:              Michael Niccum, District Engineer

 

            Subject:          Status of Capital Improvement Program Projects

_________________________________________________________________________

 

1. Third Priority Fire Protection Water Pipeline Replacement Project

 

Monterey Peninsula Engineers, Inc. (MPE) has achieved final completion for the Third Priority Fire Protection Water Pipeline Replacement Project.  Retention of $50,000 will be released to MPE 30 days after the final completion notice is recorded.  E2 Consulting Engineers provided as-built plans for the project.

 

2.  2005 Sewer Line Replacement Project

 

A final completion notice was recorded for the 2005 Sewer Line Replacement Project.  Retention of $54,695 will be released to D’Arcy and Harty Construction, Inc. within 30 days.  E2 Consulting Engineers is completing as-built plans for the project.

 

3. Pescadero Canyon Fire Road Improvements Project

 

Installation of erosion control landscaping by the Pebble Beach Company was completed.  The Pescadero Canyon fire road improvements project located off 17-Mile Drive across from the entrance to the Carmel Hill Fire Station is now complete.

 

4. Pump Station SCADA System Improvement Project

 

New instrumentation controls are operating at all eight wastewater pump stations and the SBC communication system is operating between all locations.  Instrumentation programmer Doug Buck is completing integration of the new SCADA system with the District local area computer network. 

 

 

Reviewed:     

 

General Manager: RA    Date: 12/2/05                   Agenda Item No. 10B