D
I S T R I C T E N G I N E E R ‘ S R E P O R T
August 26, 2005
To: PBCSD Board of Directors
From:
Subject: Status
of Capital Improvement Program Projects
_________________________________________________________________________
1. Third Priority Fire Protection Water
Pipeline Replacement Project
Monterey
Peninsula Engineers, Inc. (MPE) made good progress on the Third Priority Fire
Protection Water Pipeline Replacement Project completing the installation of
1,700 feet of water main line near the Monterey Peninsula Country Club (MPCC)
clubhouse. The project is substantially
complete with the exception of 600 feet of water main line that will be
installed in the new access road to the MPCC clubhouse, which is scheduled for
construction later this fall. Remaining punch
list work items are scheduled to be completed within several weeks.
MPE has earned
$1,420,799 or 90 % of the revised contract amount of $1,573,959. E2 Consulting Engineers has earned $253,401 of
the budget of $265,000 for design and construction support engineering
services.
2. 2005 Sewer Line Replacement Project
A notice to
proceed was issued on August 17th to D’Arcy and Harty Construction for
the 2005 Sewer Line Replacement Project. The contractor expects to begin field work the
last week of August on the $526,250 construction contract and estimates the
project will be completed within several months. E2 Consulting Engineers has earned $34,244 of
the budget of $89,260 for design and construction support engineering
services.
Remaining work
items for the
4. Pump Station SCADA System Improvement Project
New instrumentation controls are operating at all eight wastewater
pump stations. Alvarez Technology
telephone technicians and instrumentation programmer Doug Buck are completing integration
of the new SCADA system with the District local area computer network.
Reviewed:
General Manager: RA Date: 8/19/05 Agenda
Item No. 11B