D
I S T R I C T E N G I N E E R ‘ S R E P O R T
August 25, 2006
To: PBCSD Board of Directors
From: Michael Niccum, District Engineer
Subject: Status
of Capital Improvement Program Projects
_________________________________________________________________________
1. 2006 Sewer Line Replacement Project
Pacific Trenchless executed a construction contract for the 2006 Sewer Line Replacement Project. A pre-construction meeting is scheduled for early September and field work is scheduled to commence in October. E2 has earned $61,339 or 68 % of the budget of $89,540 for engineering design and construction management services.
2. Third Priority Fire Protection Water
Pipeline Replacement Project
Installation
of the remaining site water lines for the Third Priority Fire Protection Water
Pipeline Replacement Project was completed at the Monterey Peninsula Country
Club construction project. A final
payment of $8,400 will be made to Monterey Peninsula Engineering.
3. Fourth Priority Fire Protection Water
Pipeline Replacement Project
E2
Consulting Engineers (E2) continued final design work on the plans and
specifications for the fourth priority fire protection water pipeline
replacement project, which should be ready for bidding in September. E2
has earned $19,865 or 8 % of the budget of $249,760 for engineering design and construction management services.
4. Reclamation
Storage Tank Interior Rehabilitation Project
The interior of the 2.5 million gallon water storage
tank located of Viscaino Road near the Poppy Hills maintenance yard is
scheduled for rehabilitation this winter.
Fieldwork will be scheduled for the winter season when Forest Lake
Reservoir
5. Underground Fuel Storage Tank
Replacement Project
The underground fuel storage tanks and fuel piping at
pump stations P-3 (Spyglass Hill Road and 17-Mile Drive) and P-7 (18th
Fairway of Pebble Beach Golf Links) are scheduled for repair this fiscal year.