I S T R I C T E N G I N E E R ‘ S R E P O R T
April 29, 2005
To: PBCSD Board of Directors
From: Michael Niccum, District Engineer
Subject: Status
of Capital Improvement Program Projects
_________________________________________________________________________
1. Third Priority Fire Protection Water
Pipeline Replacement Project
Monterey
Peninsula Engineers, Inc. (MPE) made good progress on the Third Priority Fire
Protection Water Pipeline Replacement Project completing installation of 300
feet of water main line near the Monterey Peninsula Country Club clubhouse and 3,300
feet on
2. 2005 Sewer Line Replacement Project
A
recommendation to approve plans and specifications for the 2005 Sewer Line
Replacement Project and authorize an invitation to bidders is included in
Agenda Item Number 12.
Construction
fieldwork for the
4. Pump Station P-7 Wet Well Expansion Project
Mountain Mechanical
Contracting, Inc., completed the repair of a water leak on the interior of the
new 24,000-gallon fiberglass tank constructed for the P-7 Pump Station (18th
Fairway of Pebble Beach Golf Links) Wet Well Expansion Project. This was the final remaining punch list work
item and the contractor achieved final completion for the project.
5. Pump Station SCADA System Improvement Project
SBC has been on site installing the network telephone
equipment required to allow connection over DSL lines between each pump station
location and has not completed installation of a new line to pump station P-8
(Inn at
6.
A status report for construction of the Forest Lake
Reservoir Components of the Expanded CAWD / PBCSD Wastewater Reclamation Project
is included in Agenda Item Number 10.