D I S T R I C T E N
G I N E E R ‘ S R E P O R T
May 27, 2005
To: PBCSD Board of Directors
From: Michael Niccum, District Engineer
Subject: Status
of Capital Improvement Program Projects
_________________________________________________________________________
1. Third Priority Fire Protection Water
Pipeline Replacement Project
Monterey
Peninsula Engineers, Inc. (MPE) made good progress on the Third Priority Fire
Protection Water Pipeline Replacement Project completing installation of 5,200
feet of water main line and pavement restoration on
MPE has
earned $1,172,844 or 75 % of the revised contract amount of $1,573,959. E2 Consulting Engineers has earned $218,162 of
the budget of $265,000 for design and construction support engineering
services. The construction
contract requires the project be completed by July.
2. 2005 Sewer Line Replacement Project
Plans and
specifications for the 2005 Sewer Line Replacement Project are out to bid. A pre-bid conference is scheduled for May 24th
and bid opening is scheduled for June 9th. E2 Consulting Engineers has earned $22,040 of
the budget of $89,260 for design and construction support engineering
services.
Granite Construction
has scheduled fieldwork to commence the last week of May for the
4.
A status report for construction of the Forest Lake
Reservoir Components of the Expanded CAWD / PBCSD Wastewater Reclamation Project
is included in Agenda Item Number 9.
5. Pump Station SCADA System Improvement Project
SBC has been on site completing installation of the network
telephone equipment required to allow connection over DSL lines between each
pump station location. New
instrumentation controls are operating at all eight wastewater pump
stations. The remaining work items include
installation of radio antennas at several pump station sites and integration of
the new SCADA system with the District local area computer network.
Reviewed:
General Manager: RA Date:
5/20/05