1. Third Priority Fire Protection Water Pipeline Replacement Project

 

Installation of the remaining site water lines for the Third Priority Fire Protection Water Pipeline Replacement Project is underway at the Monterey Peninsula Country Club construction project and fieldwork is scheduled for completion next month. 

 

2.  Fourth Priority Fire Protection Water Pipeline Replacement Project

 

A recommendation to approve an agreement with E2 Consulting Engineers for engineering services for the Fourth Priority Fire Protection Water Pipeline Replacement Project is included in Agenda Item Number 12.

 

3.  2006 Sewer Line Replacement Project

 

Plans and specifications are out to bid for the 2006 Sewer Line Replacement Project.  A pre-bid conference is scheduled for June 29th and the bid opening is scheduled for July 18th. E2 Consulting Engineers has earned $34,832 of the budget of $89,540 for design and construction support engineering services.

 

 

 

Agenda Item No. 10B