D
I S T R I C T E N G I N E E R ‘ S R E P O R T
June 30, 2006
To: PBCSD Board of Directors
From:
Subject: Status
of Capital Improvement Program Projects
_________________________________________________________________________
1. Third Priority Fire Protection Water
Pipeline Replacement Project
Installation
of the remaining site water lines for the Third Priority Fire Protection Water
Pipeline Replacement Project is underway at the Monterey Peninsula Country Club
construction project and fieldwork is scheduled for completion next month.
2. Fourth Priority Fire Protection Water
Pipeline Replacement Project
A recommendation to approve an agreement with E2 Consulting Engineers for
engineering services for the Fourth Priority Fire Protection Water Pipeline
Replacement Project is included in Agenda Item Number 12.
3. 2006 Sewer Line Replacement Project
Plans and specifications are out to bid for the 2006 Sewer Line
Replacement Project. A pre-bid conference
is scheduled for June 29th and the bid opening is scheduled for July
18th. E2 Consulting Engineers has earned $34,832 of the budget of
$89,540 for design and construction support engineering services.
Agenda
Item No. 10B