D
I S T R I C T E N G I N E E R ‘ S R E P O R T
February 25, 2005
To: PBCSD Board of Directors
From: Michael Niccum, District Engineer
Subject: Status
of Capital Improvement Program Projects
_________________________________________________________________________
1. PBCSD Public Facilities Improvement Project
Retention of
$50,000 of the revised contract amount of $2,956,294 will be released after
submittal of all lien releases and final completion of the project is
achieved. The Paul Davis Partnership is
completing preparation of as-built plans based on contractor field notes.
2. Third Priority Fire Protection Water
Pipeline Replacement Project
A
recommendation to increase the scope of the Third Priority Fire Protection
Water Pipeline Replacement project is included in Agenda Item No. 10.
3. 2005 Sewer Line Replacement Project
E2 Consulting
Engineers visited each of the sewer lines identified for replacement with
District staff and is preparing plans and specifications for the 2005 Sewer
Line Replacement Project. The bid
documents are scheduled to be ready for consideration by the Board at its April
meeting. An allocation of $500,000 is
included in the 2004-05 fiscal year budget for this project.
A geotechnical
report has been submitted to the Monterey County Building Department as part of
the grading permit application for the
5. Pump Station P-7 Wet Well Expansion Project
Mountain Mechanical
Contracting, Inc., has prepared an acceptable plan for repairing a leak on the
interior of the new 24,000-gallon fiberglass tank constructed for the P-7 Pump
Station (18th Fairway of Pebble Beach Golf Links) Wet Well Expansion
Project. Fieldwork will be scheduled
within the next several weeks, depending on weather and PB golf links
operational considerations.
6. Recycled Water Pipeline Cathodic Protection
System Project
Remaining
punch list items for the recycled water pipeline cathodic protection system project
include submittal of final testing results, repair of damaged roadway pavement
and submittal of as-built plans. Ten
percent of the $103,000 contract will be retained until after final completion
is achieved.
7. Pump Station SCADA System Improvement Project
New instrumentation controls are operating at all eight
of the wastewater pump stations with the completion of installation work at pump
station P-3 (
Reviewed:
General Manager: RA Date: 2/25/05 Agenda
Item No. 9