DRAFT
Carmel Area Wastewater District/Pebble Beach Community
Services District
Pebble Beach Company
WASTEWATER
RECLAMATION PROJECT
MANAGEMENT
COMMITTEE
MINUTES
Meeting of
July 8, 2005
Pebble Beach
Community Services District Boardroom
1. Call
to Order
Ray von Dohren, CAWD General Manager, serving as
facilitator, called the meeting to order at 9:36 a.m. All members or alternates were present,
including: Robert Kohn and Charlotte F. Townsend, Carmel Area Wastewater
District Board of Directors (CAWD); Richard D. Verbanec and Gary D. Hornbuckle,
Pebble Beach Community Services District Board of Directors (PBCSD); and Mark
Stilwell, Executive Vice President, Pebble Beach Company (PBCo).
Others in
attendance:
Rick
Dickhaut, Administrative Services Manager/Chief Finance Officer, Monterey
Peninsula Water Management District (MPWMD)
Robert
R. Wellington, Legal Counsel, CAWD/PBCSD
Michael
Niccum, P.E., District Engineer, PBCSD
Barbara
Buikema, Accountant/Controller, CAWD
Brent Reitz, Project Engineer, PBCo
Tom Peterson, Production Superintendent, Monterey
District, Cal-Am Water Company (“Cal-Am”)
Fay
A. Webb, Secretary to the Board, CAWD
2. Period for welcoming visitors, receiving public comment regarding
matters not listed or considering changes to the agenda:
Following introductions, there were no comments from visitors or
Committee members regarding matters not listed on the agenda, and no requests
were received to change the content or order of the agenda.
3. Minutes:
Gary
Hornbuckle questioned the difference between the two references made to the
balance in the Operation & Maintenance account; one indicating a balance of
$378,299 and one indicating a balance of $258,253. Accountant Buikema replied that the higher
balance was as of January 31, 2005 and the lesser was as of May 20, 2005.
There were no corrections made to the Minutes.
It
was moved by Mark Stilwell, seconded by
4. Receive
and consider reports relating to operations and maintenance (“O & M”) of
Project:
4-A.
Treatment Plant O & M
The Committee received a written status report from CAWD Treatment
Plant Superintendent, Mark Scheiter regarding treatment plant operations.
Gary Hornbuckle questioned the excessive reports of failure of the MF
unit on “Filtrate Flow Low Low” alarm.
CAWD General Manager, Ray von Dohren, explained that at the time the
pilot plant was running with only CAWD treatment plant staff, and no attendance
by US Filter personnel, there was a
low level alarm that indicated the flow leading to the MF was low. Plant
personnel would come in, reset it and keep the unit running, ignoring the
alarm, because it had no significant impact to continued pilot plant
operation. Subsequently, the flow to
the RO unit shut down. Mr. von Dohren
advised that, at the present, now that
the project is fully staffed, US Filter, Carollo Engineers and CAWD staff have
gotten together and are investigating the cause of the reoccurring low level
alarm.
There were no further questions or comments.
The written and oral reports regarding Treatment Plant
O & M were received as informational and no action was required or taken by
the committee.
4-B. Distribution System O & M; reclaimed and
potable water use
PBCSD District Engineer, Michael Niccum, reviewed his Distribution
System Operations Report, dated July 8, 2005 and indicated that it had been a
routine period.
He pointed out that total water demand year to date is
a little below the 10-year average usage for this point of the water year. He indicated that the June flushing cycle
used 17 acre feet of potable water and that another flushing cycle is scheduled
for the following week
There were no questions regarding this report.
The Distribution System O & M Report was received for
information and no action was required
or taken by the committee.
4-C.
Consolidated Financial Statements from July 2004 through February 2005
Barbara Buikema reviewed the financial statements for
the period from July 2004 through February 2005. She stated that February is a slow time for
the Project and that there has not been a lot of activity to report. Accountant Buikema reviewed the various
account balances and account activity.
She pointed out that cash in the County O & M account is $150,000, and, in addition, there is now cash
in the newly opened account at First National Bank in the amount of
$38,000. This account will now be used
exclusively for the payment of O & M costs, with the County O & M account
acting as a sweep account to transfer funds into First National Bank
Barbara stated that the O & M revenue and Expense
account has a positive variance of $125,000 and shows a net cash income through
February 2005 of $339,000.
Ms. Buikema stated that she had no further comments to
offer regarding the financial statements and would respond to any questions the
Committee members had.
Gary Hornbuckle questioned a payment to Stone &
Youngberg for a quarterly remarketing fee in the amount of $7,900. Mark Stilwell explained that there is a
quarterly fee imposed by Stone & Youngberg, acting as broker, for
remarketing the COPs on a weekly basis. Mr. Stilwell asked when the next
principal payment would become due. Ms.
Buikema replied that it will be due July 1.
Mr. Hornbuckle stated that, upon looking at the balance sheet, it
appears that the liability for the Certificates of Participation would result
in a net loss and asked how that will be compensated. Mr. Stilwell replied that the Pebble Beach
Co. writes a check to the Project for the amount of net loss. Mr. Hornbuckle asked if eventually, the loss
would be turned into a positive amount.
Mr. Stilwell answered that it would not and, that the Company would
continue to provide the capital for payment of the COPs.
Following questions and answers, it was the consensus
of the Management Committee to accept, as submitted, the CAWD/PBCSD Reclamation
Project Financial Statements for the period July 2004 through February 2005.
5. Receive and consider CAWD/PBCSD
Reclamation Project Budget for Fiscal Year 2005-2006 (July 1, 2005 through June
30, 2006)
Barbara Buikema pointed out that the cost of water
sales reflect a 5% increase. She also
advised that there will be an increase in interest income as a result of funds
being deposited for Phase II construction in Wells Fargo Bank. She further stated that the budget includes
a 3% COLA salary adjustment for CAWD employees.
Ms. Buikema reviewed further adjustments that had been made to the
2005/2006 Budget, including the provision for earthquake insurance for
A question arose concerning the fees being charged by
Arbitrage Compliance Specialists and the actual services the company
provides. Rick Dickhaut, MPWMD, will
write a letter to Arbitrage asking them to explain why the charges are so high
and what their duties have entailed to substantiate their fee. He will also attempt to get another company
to provide the service at a lower cost.
Barbara Buikema continued with the review of the
budget and stated that the contribution to the capital reserve fund has been
increased from $5,300 to $70,000 in order to generate the funds necessary to
meet the required “sinking fund” of $2M within the next 17 years as provided
for in the financial agreements.
Barbara Buikema moved on to the Capital Budget for FY
2005/06 and pointed out that the proposed budget for capital improvements to
the advanced treatment project is estimated at $6M. Gary Hornbuckle questioned the validity of
the $6M estimate. Ms. Buikema replied
that the figure was purely an estimate.
Rick Verbanec asked how much uncertainty there was in
estimating the $6M. CAWD General
Manager, Ray von Dohren, replied that the Project had just been restarted the
previous week after some delay and, at this point, there is no way of
estimating more closely what the costs will be in the coming fiscal year. That number will be revised as the Project
advances.
Ms. Buikema presented a chart showing the reclaimed
and potable water sales since 1994. Mark
Stilwell questioned whether the figures included Cal-Am charges. Ms. Buikema replied that they did, including
fees.
Ms. Buikema reviewed the capital projects and capital
purchases planned by CAWD and the percentages to be shared by the Reclamation
Project.
It was moved by Charlotte Townsend, seconded by Mark Stilwell,
and unanimously carried, to approve
the draft CAWD/PBCSD Reclamation Project
Budget for Fiscal Year 2005/06.
6. Receive status reports concerning
Main Components Phase II (Expanded) Reclamation Project:
6-A. Planning and Design of Advanced treatment:
micro-filtration/reverse osmosis facilities
General Manager von Dohren reviewed the staff report and further
reported orally that permission had been received from the Pebble Beach Company
to resume work on the full scope of the MF/RO Project and complete the
preliminary engineering tasks. He stated
that Carollo Engineers is developing a revised project scope and, coordinating
with Camp, Dresser and McKee and US Filter, to produce a final budget for design
costs. The team is currently considering
a Project that would include somewhere around a 35% design and then moving into
a design/build type project. Mr. von
Dohren further stated that, as soon as there are elements to build,
construction will begin with additional design to be done at the same
time. Other costs of the MF/RO
design/build will be determined and presented to the Pebble Beach Company for
review, negotiation and approval. He
stated that the only uncertainty at this time is whether the Pebble Beach
Company or CAWD will hold the contract with Camp, Dresser and McKee for
construction of the Project. Mr. von
Dohren said that the supply part of the Project with U.S. Filter will be a
subcontract with Camp, Dresser and McKee or the Company or, CAWD will purchase
the equipment directly. Mr. von Dohren
advised that work done in the last week was primarily getting the team back
together. He said that the first item
to address is the problem of the low water alarm and the fact that the R/O unit
shut off. CAWD staff could not determine
if the low alarm was the result of a low water condition or a bio-fouling
occurring in the microfilters. The
preliminary results are that it was caused by a low water condition. Mr. von Dohren explained the need for the
chlorminator in regulating the amount of chloramines in the effluent, and in
feeding chloramines to the MF/RO facilities.
Mr. von Dohren indicated that there is a need for modifications to the
secondary plant in order to make sure that the plant will consistently
denitrify the effluent to control the amount of ammonia entering MF/RO system,
but that Carollo Engineers have
indicated that there is no necessity to modify the outfall to secure the proper
dilution of effluent.
Mark
Stilwell asked what the next step would be in resuming the Project. Ray von Dohren replied that, prior to the
company agreeing to start the project again, CAWD staff met with Carollo to see
if there was a way to reduce the design cost by modifying the type of design.
It was decided that, rather than proceeding with a typical design contract,
which would involve a ten percent, fifty percent, seventy percent design
review, making comments regarding the design and then passing them back to the
engineer for changes, there would be a series of workshops at key points where
Carollo would present the design to staff, and allow staff one week to work
with Carollo to make any recommended changes.
Carollo believes they can save a lot of time and cost by doing the
design in that manner, rather than the traditional way. CAWD staff feels that would work very well
and are willing to work with Carollo in that manner. Carollo is working now with U.S. Filter and
CDM on elements of the design in an effort to finish the scope and present
revised costs.
Mr.
von Dohren also advised that the basic environmental work still has to be
completed as well as using Carollo’s data to evaluate the environmental impact
from the RO concentrate that will be discharged into the Bay. Mr. von Dohren stated the last thing would be
to work with the Regional Board to revise our waste discharge permit. CAWD now has a reclamation permit to supply
reclaimed water to the Project. He
advised that the criteria which must be met under that permit will not change,
but that it will still be necessary to obtain a new permit. The new permit will have no requirements for
the elimination of salt, but there may be requirements for the brine.
Gary
Hornbuckle pointed out that during the prior meeting of the Reclamation
Management Committee meeting the budget for the Project was upwards of
$20M. He asked if the Pebble Beach
Company had agreed to accept the additional cost. Mark Stilwell advised that the Company,
Carollo Engineers and CAWD, working together as a team, has brought the cost
down to approximately $18M. Ray von
Dohren said that CAWD will run the Project the same as any other project that
they might have, which will give them the opportunity to monitor costs. He said that the concern of CAWD and PBCSD is
the fact that, at the completion of the Project, both Districts will assume
responsibility for water quality and quantity and, that will be a major factor
in determining and controlling costs.
Mr. von Dohren stated that a factor in determining costs will be
maintaining proper capital; implementing a renewal and replacement program,
which ultimately all the golf courses have to pay for; and what the level of
operation and maintenance costs will be.
Brent
Reitz asked when Carollo Engineers would be back with the initial design
cost. Mr. Von Dohren replied that he
would expect to hear from Carollo within the next couple of weeks.
6-B.
PBCSD
District Engineer Mike Niccum, in addition to his written report, presented a
slide show, together with comments, showing the progress made to date on
construction of the Reservoir. Mr.
Niccum answered questions from the Committee during the presentation.
6-C. Project
Financing Status
Mark Stilwell reported that the Company had closed its third batch of
water sales, proceeds of which were deposited with the Wells Fargo Bank account
for construction funds. He further
reported that three draw requests had been made, including one from CAWD. Mr. Stilwell stated that the price of water
sales would be increased from $200,000 to $250,000 per acre foot as of July 15,
2005, due to the increased cost of the advanced treatment project. He hoped by raising the cost of the water,
that people who were undecided about purchasing water would make a decision to
do so. Mr. Stilwell advised that he had
contacted Wells Fargo Bank to obtain bank statements on the construction fund
account
Mr.
Stilwell had questioned staff at the MPWMD for information regarding how much
of the newly purchased water is currently being used. Rick Dickhaut of the MPWMD stated that he
will follow up on the matter and report back to Mr. Stilwell.
Robert
Kohn asked the status of the lawsuit presented by Attorney Rosenthal regarding
the possible applicability of the “Robles del Rio Agreement” to the MPWMD’s
approval of the PBCo. water sales. Mark
Stilwell reported that it is not an active lawsuit, but a threatening letter
which has not been pursued so far.
Mark
Stilwell reported that there are several parties outside of
There
were no further questions, comments or action taken by the Committee.
7. Receive Miscellaneous Information or
Announcements from Members, Staff or Visitors:
Mark
Stilwell reported that he is working on the issue of stormwater runoff into the
ASBS which also involves
Ray
von Dohren reported on the CCLEAN meeting which he had just attended. He stated that the CCLEAN data up to this
point was indicating that the major impact of pollution into
Michael Niccum invited anyone interested in
looking at the Reservoir to join him after the meeting.
There
were no further reports or announcements from Committee members, staff or
visitors.
8. There was no need for a closed
session.
9. Adjournment & Next Meeting Date:
It was moved and seconded by Mark Stilwell and Rick
Dickhaut, and determined by consensus of the members, that the Reclamation
Management Committee adjourn to its next regular meeting on Friday, September
16, 2005 at 9:30 a.m. in the PBCSD Boardroom at Forest Lake and Lopez Roads,
Pebble Beach.
Respectfully submitted:
Fay A. Webb
Secretary to the Board
Carmel Area Wastewater District